Turbine |
Acquire from manufacturer and turbine type inquiry |
Tower (anchor) |
Tower is 8000-10000 RMB/t and anchor is 12000-13500 RMB/t. Refer to the recent bid price of the same region. |
Hoist |
It is related to hub height. It is about 300,000 RMB for 90 m and 550,000 RMB for 140 m. Depending on the actual situation, add a large-scale device in and out fee, 300,000 - 500,000 RMB for centralized project and 1,000,000 - 1,500,000 RMB for distributed project. |
Turbine transformer and low-voltage cable |
It is related to turbine transformer model and cable type. Generally, the price is 110 - 130 RMB/kW and the turbine transformer is 200,000 - 300,000 RMB. |
Foundation (not including anchor) |
It is related to turbine hub height and geological condition. The price of a natural extended foundation is 500,000 - 700,000 RMB and the price of a pile foundation is 1,000,000 -1,200,000 RMB. |
Platform |
It is related to terrain and geology. On flat ground, the price is 10,000 - 100,000 RMB for a platform and 100,000 - 300,000 for hilly area. |
Route |
The price of newly constructed route on flat ground is 150,000 - 300,000 RMB/km, for rebuilt and expanded route on flat ground is 100,000 - 150,000 RMB/km, for newly constructed route in hilly area is 300,000 - 600,000 RMB/km, and for rebuilt and expanded route in hilly area is 200,000 - 300,000 RMB/km. |
Infield power line |
The price of 35 kV cable is 300,000 - 400,000 RMB/km. The price of 35 kV aerial on flat ground is 350,000 - 450,000 RMB/km. The price of 35 kV aerial in hilly area is 400,000 - 600,000 RMB/km. |
Booster station |
35 kV switching station: 6 million RMB 110 kV - 50,000 preassembled substation: 15 million RMB 110 kV - 100,000 preassembled substation: 20 million RMB 220 kV - 100,000 preassembled substation: 25 million RMB |
Forest and land levy |
Refer to the project price of the same category in the same region. It is recommended to collect levy price information during feasibility study material collection. |
Budget reserve |
The ratio range is 1-3%. Input 2% in feasibility study phase and 1.5% in initial design phase. |
The early-stage expense, reconnaissance expense, design expense, project management expense, etc. |
The expenses mentioned here are related to wind farm capacity and owner management level. |
Environmental impact assessment and water conservation expense |
The expenses mentioned here are related to the environmental impact assessment and water conservation policy and are closely related to wind farm capacity and route length. Refer to the price list in the environmental impact assessment and water conservation report. |
Outgoing power line |
According to the project phase and condition, estimate the price based on outgoing length and unit cost or calculate it based on design scheme. |