Siting Result Selection
After the siting calculation is completed, select the substation siting object. The result of substation siting is displayed within the siting scope. The five sites marked by red are the first five substation siting recommendations with most economic value.

Double-click the substation siting object to view the economic result of substation siting.

- Substation location
-
Located at the steep slope
-
Located at the valley (This is the area with great precipitation where the rain might gather.)
-
Distance to avoiding range (For substation location without definition of buffer area, it should be located next to the boundary of avoiding range.)
-
Located in other unspecified avoiding range (such as lake, river, tomb, etc.)
-
- Transportation condition
For project in hilly area, the substation site might be at the hill top. The maintenance and operation factors should be taken into account. By substation siting, additionally select the sites close to the road on the hill and at the bottom of the hill for the final determination of site reconnaissance.
Considering the factors mentioned above, adjust the substation site within the 200 m scope around it. The adjustment within this scope would not bring out disruptive impact on the siting result.