Customizing Budget Estimation Parameters
- Click the economic evaluation model in the project pane.
- Click the expand icon 《 to open the operation pane.
- Click the Operation tab.
-
Select Customize budget parameters in the
Budget Estimation and Power Sales Parameters
area.
- Input the value of unit static investment.
-
Select Associate wind farm scheme or Customize wind farm parameters.
- Associate wind farm scheme: Select a wind farm scheme in the table below and configure power sales parameters.
All the wind farm layout schemes in the project are listed in the table, and their capacity and equivalent full-load hours are displayed.
If the wind farm scheme you select has been associated with access station, the user configuration of access points and access stations are automatically loaded into the power sales parameter configuration window. If no access station is available, you need to configure users manually.
For details of power sales parameter configuration, refer to the section Configure power sales parameters.
- Customize wind farm parameters: Input the wind farm capacity and equivalent full-load hours, and configure power sales parameters.
In this condition, you need to configure users manually.
For details of power sales parameter configuration, refer to the section Configure power sales parameters.
- Associate wind farm scheme: Select a wind farm scheme in the table below and configure power sales parameters.
- Click the Done button to save the settings.
- Expand the Economic evaluation configuration area, click the Configurtion button, and set up parameters in the Economic Evaluation window. Refer to the section Configure economic evaluation parameters for details.
- Expand to show the Stock equity institute configuration area, input the No. of shareholders and their shares and investment, and click Done to save the settings.
- Click Calculate to start the economic evaluation. After the calculation is completed, the parameters under the Calculate button displays the economical features of the wind farm, such as total installed, capacity, equivalent full-load hours, capital IRR after tax, total investment IRR, after tax, LCOE, total investment NPV after tax, and capital NPV after tax.