Checking Access Result

When the calculation is completed, check the single-line design and relative economic parameters.

  1. Open the operation pane to check the overall economic parameters of access plan. Including total access capacity, access IRR, access NPV, discounted year, discounted rate, limiting generation capacity, abandon access point, and abandon access machine.
    • When all accessible capacity of the grid-connected substation has been accessed, or the economic value of this access is low, this substation or the access point in this substation is abandoned.
    • When the turbine is of low economic value or cannot be accessed because all accessible capacity has been assigned, the turbine is abandoned.
      Note: To determine whether to abandon an access point or turbine based on its economic value, the NPV of the related access points or turbines are compared and only that with the optimal economic value is reserved.
  2. Double-click the WTG group object in the project pane. The WTG group Overview page opens.
  3. Click the Single-Line Design tab to check the single-line graph. Single-line graph is a demonstration of the access scheme between turbines and substations, and the grid-connected substation is matched. You can edit the topology or match the substations. Refer to the section Manual Configuration of Single-Line Topology for more details.
  4. Click the Access Economy tab to check the relative economic parameters. The overall economic parameters and those of each access point are both demonstrated.
  5. Click the Download button to download the parameters into a txt document.