Version 6.3.0¶
Greenwich v6.3.0 has been released 12th March, 2019.
Main updated modules are:
- Added economic evaluation in the self-served power production mode
- Support feasibility study report generation for new economic evaluation mode
- Optimize some UIs on electric single-line design
- Fixed some existing issues
Please check the user manual via this link.
For more information, please check the following content:
Economic Evaluation¶
- Improved economic evaluation to support both centralized and distributed wind farm project.
- Added calculation on self-served ratio of power production.
- Added economic evaluation in the self-served power production mode.
- Added analysis on user earnings.
- Optimized the interaction.
Feasibility Study Report¶
- Adopted new economic evaluation model to support both centralized and distributed wind farm project.
- Added the self-served power production mode.
- Added multiple long-term loan methods.
Access Plan¶
- Added highlight display in electric single-line graph: When hovering your pointer over the substation object, the upper-level line connected with this object is highlighted.
- Added a warning for turbine type alternation in electric single-line graph.
- Fixed bugs in electric single-line graph display.