Checking Results
-
Double-click the WTG group object in the project pane. The Overview page opens displaying the AEP calculation results.
The AEP calculation result consists of:
Select interested parameters in the Column Settings list to add them in the table. Refer to the section Configuring Turbine Property for more details.
- Click the PBOM tab to check the PBOM details of each turbine.
-
Add materials in the material tree.
- Select the material group No. and material No..
- Input the engineering quantity.
- Input the price.
- Click the + icon to add a material item.
- Click Save at the left top of this page to save the settings.
-
Edit the quantity and price.
- Double-click the cells under the Quantity and Price column to edit their values.
- Click Save at the left top of this page to save the settings.
-
Delete the material.
- Click the delete icon at the right end of an item to delete the respective material.
- Click Save at the left top of this page to save the settings.